Hrvatska elektroprivreda (Croatian Electricity Company) has launched a tender for the construction of the main structures of the Kosinj hydroelectric system and the supply of equipment. The estimated value of the work is €480 million excluding VAT, and the tender documentation has been published in the Electronic Public Procurement Gazette.

The tender relates to the construction of the main structures of the future hydroelectric system, while certain replacement infrastructure measures have been separated from this procedure. HEP’s main project is designed through a total of 18 building permits, three of which relate to replacement structures — the Studenci – Sklope and Kosinj bridge – Bakovac roads, and the Bakovac – Lika tunnel and channel. The remaining 15 building permits relate to the main structures of the hydroelectric system, and the aforementioned replacement structures are not the subject of this tender. The Bakovac – Lika tunnel and channel are already under construction, as is part of the accompanying road infrastructure.

The project includes the construction of a new reservoir with a surface area of 11.45 square kilometres in the Perušić municipality, downstream of the existing Kruščica lake and Sklope hydroelectric plant. The planned capacity of the reservoir is approximately 340 million cubic metres of water, which will be retained by three embankment dams with clay cores. The highest dam is planned at Kosinj, with a height of about 58.5 metres and a length of about 400 metres, while the dam at Bakovac is to be 55 metres high and 450 metres long. The Sedlo dam will be 22.4 metres high.

The project provides for a new Kosinj hydroelectric plant with two turbines of approximately 22 and 12.6 megawatts of power. The first turbine will operate when the lake is full, and the second when the water level is lower. At the existing Sklope hydroelectric plant, the facility will be reconstructed and the turbine replaced — a new turbine with a maximum power of approximately 24.7 megawatts will be installed instead of the old one, while the Sklope plant currently has an installed capacity of 22.5 megawatts. The Sklope hydroelectric plant’s machine hall is about five metres above the highest level of the future lake, and a new spillway is planned on the Sklope dam.

The project also includes sealing the ground beneath the dams and along the lake edges to reduce water losses. A cement mixture will be injected through boreholes up to 100 metres deep, over a total length of approximately 5.6 kilometres. The contract with the contractor will last 75 months, and construction is planned over six years. The first year is allocated for preparatory works, the following four for the construction of the dams and hydroelectric plant and ground sealing, and the final year for the initial filling of the lake and trial operation of the plants. Clay for the dam cores can only be installed from April to October.

The deadline for applications is 1 March 2027, and the tender has been published as a negotiated procedure. Bids will be evaluated based on price, which carries 90 points, and the guarantee period, which carries 10 points and can range from two to five years. Companies will have to attach a bank guarantee of €14.4 million with their final bid. Interested companies can submit requests to participate by 1 March 2027, after which HEP will invite companies that meet the conditions to submit initial bids. Following negotiations, HEP will request final bids, and only companies invited to the second phase of the procedure will receive detailed technical specifications, a cost schedule and a draft contract.

The Kosinj hydroelectric system is part of the second phase of the expansion of the existing Senj hydroelectric system, which has used the waters of the Lika and Gacka rivers for electricity production since 1966. HEP plans to utilise the remaining hydroelectric potential of the Lika river, increase electricity production and regulate flooding in the Kosinj valley. The HES Senj 2 project is expected to increase the installed capacity of the system by 412 megawatts and provide an additional 320 gigawatt-hours of electricity annually. Implementation of the project includes the construction of replacement infrastructure and the relocation of the population from the area of the future reservoir.

The area is sparsely populated due to frequent winter and spring floods, and the largest settlements are Gornji Kosinj and Mlakva. Filling the lake would permanently submerge one county road and one local road, as well as nine local substations, thereby severing the electrical grid connection to the settlement of Bakovac. HEP is obliged to relocate the population from the area of the future lake and to build a new electrical grid and substation for Bakovac. A replacement road from Kosinj bridge to Bakovac is already being built near the future lake, the road from Studenci to the Sklope hydroelectric plant is being renewed, and the construction of a tunnel to divert the Bakovac stream into the Lika is underway. These works are not covered by this tender.

The idea of expanding the Senj hydroelectric system first emerged in the 1980s. The project was subsequently halted and only resumed during the second decade of this century. HEP obtained a location permit in 2019.