Hrvatske autoceste (HAC) (Croatian Motorways) have received four bids for the replacement of protective crash barriers on 47 kilometres of motorway from Zagreb towards Lipovac, on the section between the Lipovljani and Nova Gradiška junctions. The bids were opened on Friday, and the minutes of the opening were published in the Electronic Public Procurement Gazette.

The lowest bid was submitted by the consortium of Signalinea from Bakar and TIM Topusko, amounting to 9.3 million euros excluding VAT. This is approximately a quarter lower than the estimated value of the works, which stands at 12.9 million euros excluding VAT. The highest bid, 10.7 million euros, was submitted by Split-based Prvi treptač. Alongside them, bids were also submitted by the consortium of Pismorad and Signalizacija HR, and the consortium of Fracasso Production and Fracasso Deutschland. HAC is now reviewing and evaluating the received bids.

According to data from the Ministry of the Sea, Transport and Infrastructure, the section from Lipovljani to Nova Gradiška has poor safety indicators. HAC is aligning the barriers on this section with current regulations and European standards. The installation of more than 170 kilometres of new steel and concrete barriers along both edges of the carriageway and in the central reservation is planned. The goal is to reduce the number of fatalities and injuries in traffic accidents.

The works will last 18 months from the contractor's entry into the site. During this time, drivers will encounter closed lanes. For works along the edge of the carriageway, the hard shoulder is usually closed, while for works in the central reservation, the overtaking lane is closed in both directions. Works can be carried out during the day and at night, and on weekends and public holidays, although they may be restricted during the tourist season.

The project is co-financed to the tune of 85 per cent by the European Union's Connecting Europe Facility (CEF). This is the second tender for the same works, after HAC issued the first one in 2024. The State Commission for the Control of Public Procurement Procedures annulled the decision on the selection of the contractor following an appeal by one bidder, and HAC cancelled the entire procedure in March.