The Church of St Krševan in Zadar has once again been put into service for the holding of liturgical celebrations from Monday, 23 November 2026, the vigil of the feast of St Krševan. St Krševan is the patron saint of the city of Zadar.

The Media Office of the Zadar Archdiocese asked the Regional Conservation Service Zadar to specify what the process of renovating the Church of St Krševan has included. The former name of the Regional Conservation Service Zadar was the Conservation Department in Zadar. The press release from the Conservation Service Zadar is titled “Protective works on the Church of St Krševan in Zadar”, signed by Igor Miletić, head of the Service, and dated on the feast of St Krševan, on Tuesday, 24 November.

The Church of St Krševan is one of the most significant monuments of Romanesque architecture in Dalmatia. It was built in the second half of the 12th century as a three-nave basilica of the Benedictine monastery of St Krševan, which was located on the north side of the church and has been completely destroyed. The bell tower in front of the façade was begun in the 15th century, but was never completed. At the beginning of the 20th century, from 1911 to 1914, the church was included in a renovation and conservation led by Ć. M. Iveković.

Protective works were carried out during the 1970s, when the frescoes inside the church were restored. In 2003, structural repair and reconstruction of the apse roofs were carried out, and a report was produced for the repair, restoration and conservation of the external cladding of the apses. In 2004, works cleaned the stone architectural decoration and external wall surfaces of the church, and the capitals and columns of the gallery of the central apse were restored and conserved.

Following damage to part of the roof of the main nave, a complete analysis of the state of the church was carried out in 2005. The analysis determined numerous damages such as erosion of plaster on the walls, cracks in the walls, distortion of arches and damage to window frames. Activities on the renovation of the church began in 2006 with the repair of the roof structure of the central nave. Due to the collapse of part of the roof structure, complete renovations of the roof covering of the central and both side naves of the church were carried out in 2008 and 2009.

During 2013 and 2014, a revision of the complete installations was carried out, and projects for strong and weak current and lightning protection were produced. After the revision of the installations, the main electrical conduit was laid and the basic network of installations for the lighting of the church was produced. At the same time, the interior of the bell tower was cleaned of organic accumulations, and grilles were installed on the bell tower and the openings of the church.

In 2015 and 2016, a revision of the fresco paintings in the apses and on the north wall inside the church followed. The necessary conservation-restoration interventions on the frescoes were carried out by the Croatian Institute for Conservation (HRZ). During 2017 and 2018, the HRZ carried out investigations of the state of the stone sculpture inside the church and photogrammetric measurement of all altars in the church. Based on the results of the investigations, a conservation-restoration report for the renovation of the interior was produced.

In 2019, works on the main portal followed, which were completed in 2020. In the following year, complete conservation-restoration works were carried out on the stone arcades inside the church. That year, works on the repair of the stone paving of the church and crypt also began, which were particularly demanding due to constant contact with water. They were carried out for the purpose of maintaining the programme of the Concert Office in Zadar and in cooperation with the City of Zadar.

Works on the stone sculpture of the side altars took place from 2022, when the side Altar of the Sorrowful Virgin was repaired. During 2023 and 2024, conservation-restoration works were carried out on the remaining side altars. Works on structural repair, as well as restoration-conservation works on the main altar of the church, were carried out in two phases: the first phase in 2025 and the second phase in 2026. In the last year, sampling of plaster on part of the south nave of the church was carried out.

The project for the arrangement of the interior is entering its final phase, when, before plastering the interior, the necessary electrical installations will be installed in the church. Protective works on the Church of St Krševan over the years have been largely financed from the programmes of the Ministry of Culture and Media of the Republic of Croatia. The works were carried out under the constant supervision of the Regional Conservation Service in Zadar and with the participation of the City of Zadar in certain interventions.