Intensive work continues at the construction site for the reconstruction of the Širina intersection in Solin, with the outlines of the new "Jadro" bridge becoming increasingly visible. This is the most important part of the project, which will significantly speed up traffic on the approach to Split. Activities have been extended to the bridge abutments, structural elements at the ends of the bridge that connect it to the approach roads, while preparations are simultaneously underway for the next major phase of the project, which involves the installation of the steel span structure.

In the past few weeks, three more concrete column heads at the tops of the pillars have been completed, increasing their number from four to seven out of a total of eleven. The construction of pillars at another pier location has also been finished, meaning pillars are now built at two of six planned positions. Previously, four of the six pile caps, which are part of the foundation system of the future bridge, were also completed.

The works are being carried out by the company Texo Molior, and since the start of its work in Solin, a total of 1775.75 cubic metres of concrete has been poured. Currently, 50 workers are engaged on site, including operational workers, engineers and other construction-technical staff.

Chief site engineer Stjepan Kapural emphasises that they will continue with the construction of the remaining elements of the substructure until the end of the year to prepare the pier locations to receive the superstructure of the bridge. The first elements of the steel structure will be installed in the first part of 2027.

The construction of the new "Jadro" bridge is the first phase of the reconstruction of the Širina intersection, one of the busiest road junctions in Croatia. The completion of the bridge will enable traffic to be diverted to the new road, thereby creating conditions for the continuation of the reconstruction of the existing intersection and the repair of the existing bridges.

According to the contracted schedule, the completion of the first phase of the project, namely the new "Jadro" bridge, is scheduled for August 2027, while the completion of the entire project is planned for February 2028. The investor in the project is Hrvatske ceste (Croatian Roads), which in March this year announced that a notice of contract termination for the project execution of works at Solin's Širina had been sent to the DIV group, owned by Tomislav Debeljak. Since Texo Molior started working in Solin, the story is finally moving forward.